Common contractor errors
This article highlights some common contractor errors which should be considered when approaching construction.
Contents |
[edit] Step by step guidance
[edit] Responsible construction practices
Considerate Construction scores count and it is the last assessment which contributes to the final BREEAM assessment. This can be forgotten.
[edit] Construction site impacts
The contractor must be aware from the beginning what they are required to monitor. It is usual for all energy and water use to be monitored but transport is less common. The contractor should be informed about what needs to be in place to achieve the credit. Sometimes the required units are not provided.
Most contractors have a ISO 14001 certificate. This should be part of the contractors prelims as without an ISO 14001 one credit cannot be achieved.
Contractors may have pollution prevention policies but may not be familiar with the environmental checklist and so should have this highlighted to them as soon as possible.
All contractors should be using timber in line with the government procurement policy but sometimes there is a misunderstanding between timber used in the project and timber used on site.
[edit] Stakeholder participation
Building User guide, all contractors will be familiar with O and M manuals and can be mistaken thinking they are appropriate here. The Building User Guide requirements should be highlighted to them, they are found in the BREEAM manual. It is important that each relevant heading is addressed. This document is often left to the end of the construction and then drags on. If the guide is begun early it should not be as much of a burden at the end. There are companies available which will out a BUG together for a fee.
[edit] Indoor Air Quality
Minimising Sources of Air pollution. The architect’s specification should detail compliant products, sometimes specific products. The contractor may be unaware of the importance of the standards detailed and the effect a change could have on the BREEAM score. The contractor should be made aware that any change in product needs to still be compliant. Collection of manufacturers datasheets as the products are procured is helpful to negate a paperchase exercise at the end of the project.
[edit] Thermal Comfort
A change to window choice can mean the thermal comfort levels in the development fail. Contractors should involve the engineers in changes like this and check which BREEAM credits are being targeted.
[edit] Acoustic Performance
The acoustician will carry out calculations and make recommendations for compliance during the design. The contractor can forget that when the acoustician carries out testing at the end of construction, if the building does not pass remediation must be carried out and this is a cost. Careful consideration to the acoustician’s recommendations should help avoid this.
[edit] Energy
The contractor should be wary of changes to insulation, lighting, u-values these can have impacts on the energy model and resultant BRUKL. Energy monitoring can be queried as more metering means more of a cost. The metering provision should be checked that it meets the criteria and is not in excess of it if cost is an issue.
[edit] Water consumption
Sometimes sanitary fittings are changed without consideration to flow rate. The flow rate and flush volume is what dictates the achievement of Wat 1. Increase in volumes can mean loss of credits.
[edit] Responsible Sourcing of Materials
It is important that an exercise to determine the achievable responsible sourcing credits is carried out early and where possible with the contractors input. The contractor will likely know who will supply their materials and so the level of responsible sourcing will be known. Certificates should be collected as materials are procured to negate a paper chase at the end of the project. Credits are easily lost here because suppliers were not compliant or did not provide certification.
[edit] Waste
Overly ambitious project managers or design teams can sometimes commit to difficult waste reduction levels. If possible, the contractor should have input before commitments are made or be fully aware of the requirement in their pre-lims. There is no way to get waste credits back.
[edit] Ecology
The contractor if targeting ‘Long term impact on biodiversity’ will need to have a biodiversity champion. There are training requirements and a log book which must be carried out. If one item is not completed the credit is likely lost.
[edit] NOx Emissions
A change in plant can have a big impact on the Nox emissions. Where any change is made the calculations should carried out again.
[edit] Questions to ask while seeking compliance
Is the Contractor aware of the requirement to achieve BREEAM?
Are BREEAM requirements part of the contractor’s contract?
[edit] Tools and resources
BREEAM Manual and Knowledgebase
[edit] Tips and best practice
When the contractor has a sustainability champion or person dedicated to environmental management and BREEAM the process often runs much smoother.
[edit] Typical evidence
Formal letters – signed, dated and on headed paper
Extracts from the Pre-lims. Must be clear they are for the specific project
Manufacturers literature
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Emma Houston 11:16, 18 Jan 2018 (BST)
Featured articles and news
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.